PROJECT BACKGROUND & OBJECTIVES
D and J bought a property in the Crestwood neighborhood with dreams of building a net zero home to fit their family's needs. They would like a 3 bedroom 3/3.5 bath home with an office that doubles a guest bedroom when family is in town. The home must accommodate a large kitchen, a walk-in pantry, a dining room for 8-10 people. In addition to main the residence, they would like an ADU. The ADU should be designed with aging in place in mind. It must include a bedroom, bathroom, living space, small kitchen, and washer dryer combo. The master plan should consider covered parking, pool, landscape, covered porch between guest house and main house.
​
DESIGN GOALS BY PRIORITY
-
The main residence should have 4 bedrooms 3-3.5 bath with an office that doubles as a guest bedroom and ideally be a net zero home.
-
Guest House/ ADU should have 1 bedroom, 1 bathroom, a small kitchen and living space.
-
Covered Parking, does not have to be a garage.
-
Site design to include a possible pool location and landscape concept.
​
PROJECT DELIVERABLES: WHAT’S IN?
-
New residence and ADU with CLT construction.
-
New water meter.
-
A covered porch that connects the ADU and main house.
-
Carport for 1 vehicle in option B
-
New driveway and apron.
​​
OPTIONAL UPGRADES
-
Prefinished wood floors for the main house and ADU
-
Heated floors in the primary bathroom.
-
Remove 15' side yard access to accommodate a larger courtyard in option B.
-
Upgrade to metal cladding +/- 85k.
​
PROJECT EXCLUSIONS: WHAT'S OUT?
-
Solar Panels design and installation
-
Pool Management and Construction
-
Landscape Design and Construction
-
Moontower Design Services
-
Consultant Services (structural, geotechnical, mechanical, etc)
-
Regulatory Fees (permitting, sidewalk fee in lieu, etc)
​
PROJECT CONSTRAINTS:
-
CLT construction requires heavy duty machinery and it is ideal to have 15' side yard access for panel installation.
-
Current pricing reflects a pier and beam foundation, where the CLT floor panels must be 18" above grade for termite control. This in turn will require step to the house and a longer visitability ramp.
​​
PROJECT ASSUMPTIONS:
The existing water tap is located on the property line and will need to be relocated.
Waste water line is touching the property line and is not in a CRZ of a protected tree. Therefore, it will not need to be relocated.
Soil is in good condition and will be able to use helical steel piers for the foundation.
​
SCOPE ASSUMPTIONS:
-
Cork is the exterior finish and insulation for the walls and floor. Wood fiber board to be used at the roof.
-
Roof finish is standing seam metal.
-
Cabinetry is semi custom paint grade.
-
Exterior and interior finishes don't require sealing or paint.
-
Entry level triple pane windows.
-
Interior walls, floors, and ceiling finish to be CLT.
-
Tile installed at shower floors and walls only.
-
No base boards needed. Jamb extensions at windows and doors.
-
Richlite countertops and backsplashes at the kitchen and bathrooms.
-
Assumes standard pre-wire low voltage package for internet, excludes LV lighting package.
-
Assumes water filtration system.
-
Assumes variable speed forced air ducted mechanical system with ERVs and dehumidifiers.